Scope of Work:
- Top-Side Equipment Installation & Modification:
Detail design, procurement (excluding ES Pumps) transportation, and construction & installation of the topside activities and commissioning of the entire system and execution of the necessary platform modifications.
- Chemicals handling & re-filling system Upgrading:
Design, Supply, installation and top-side modification of portal feed containers. The work shall include engineering, procurement, construction; installation and top side modification of Portal feed containers on both DP3 & DP4.
- Antiscale Inhibitor Injection Skids Replacement:
Design, supply and installation of No.5 antiscale skids complete with, steel structure supports, equipment, tubing, valves, control panel and E&I equipments to replace the existing old three onboard DP4 and two onboard DP3.
|