Replace Transformers for CP’s and Oil Wells
Reference: MTC-35/2019 9/11/2019, Location: Africa
Category: Transformers
Scope of Work
The company announces its need for Replace transformers for CP’s and oil wells at GOSP5 & GOSP6.
Description: - Supply and install 2MVA, 34.5/11KV power transformer at GOSP6. - Supply and install 2MVA, 34.5/11KV power transformer at GOSP5 ( transformer available at site). - Design, supply & install (3) substations with accessories, one 36 KV and two 12 KV at GOSP 5 & 6. - Design, supply & install fire detection & firefighting system for the substations and transformers. - Design, supply & install required cables with accessories Design and install all civil works for substations, transformers ……….etc. - Perform all the required test and commissioning. - Disconnect the old equipment and transported to warehouse yard.
|